| 1997
|
July |
White Paper 'Scotland's Parliament' published |
December |
|
December |
Exhibition of short-listed sites in Edinburgh and Glasgow |
|
January |
Site Selected: Holyrood announced as site for new building
Designer Competition: launched |
March |
Designer Competition: 70 submissions
12 practices selected for first interview |
April |
Cost consultants appointed and first draft building user brief issued
Archaeology at Holyrood: Archaeological work commenced |
May |
Designer Competition: 5 practices invited to prepare conceptual ideas |
June |
|
July |
|
September |
Site formally purchased from Scottish and Newcastle |
October |
Demolition work started on site
Designs on Display - Public exhibition of outline design proposals |
|
January |
Large scale archaeological excavations commence |
April |
Preconstrucion work begins on site
Designs on Display: Public exhibition of final scheme designs |
May |
Launch of Hoardings Artwork initiative (Future Face of Your Parliament) |
|
June |
Responsibility for the project transferred from Secretary of State to the Scottish Parliamentary Corporate Body
1st Parliamentary debate on the project
Demolition works completed |
July |
Main construction work began on site |
September |
Revised chamber design agreed |
October |
First pour of concrete for substructure of MSP building including car park
Children's artwork unveiled on site hoardings |
November |
First Tower crane arrived on site |
|
March |
Spencely Report published
|
April |
Construction of MSP building frame started
2nd Parliamentary debate on the project |
June |
1st vaulted ceiling of MSP building installed on site
Holyrood Progress Group established |
July |
Death of Enric Miralles
|
September |
Auditor General reports on Holyrood |
October |
New Parliament Building Visitor Centre opened
Death of Donald Dewar, First Minister |
December |
Contract for Kemnay Granite awarded |
|
January |
MSP accommodation topped out |
May |
3rd Parliamentary debate on the project |
June |
4th Parliamentary debate on the project |
|
September |
First beams for Debating Chamber roof installed |
October |
First of the MSP feature windows installed |
November |
New Parliament Building Visitor Centre closed |
December |
Building Information Centre opened at The Tun |
|
March |
Construction began of vaulted roofs in the committee rooms. Completion of beams and steelwork for chamber roof. Steelwork in the lobby roof in place. |
June |
Lord Fraser of Carmyllie, former Lord Advocate, appointed to lead investigation into cost of the new Parliament building |
July |
SPCB started monthly progress reports for Finance Committee
|
December |
Chamber crash deck removed
MSP Offices completed
Queensberry House building work completed
|
|
|
January |
North elevation of Canongate Wall is completed
Debating Chamber ceiling presented to Media |
March |
Last tower crane leaves Holyrood site |
May |
Installation of desks and carpet in the Debating Chamber begins
|
August |
Staff move in to Holyrood Building |
September |
Holyrood Inquiry Report published
Scottish Parliament met for first time in Holyrood |
October |
|
November |
Holyrood reached 100,000 visitors |